Question: A project manager is managing a project that has reached the end of the planning phase. The work scope has been agreed to and definitive
A project manager is managing a project that has reached the end of the planning phase. The work scope has been agreed to and definitive cost estimates have been completed for the project. The total estimated cost of the project is $100,000. It is reasonable to expect that the project will not cost over which of the following values?
a. $100,000
b. $110,000
c. $125,000
d. $175,000