Question: A project manager is overseeing a project with a total budget of $5,000,000. The project is halfway through its timeline with the following costs incurred:
A project manager is overseeing a project with a total budget of $5,000,000. The project is halfway through its timeline with the following costs incurred:
- Actual Costs to Date: $2,500,000
- Planned Value to Date: $2,400,000
- Earned Value to Date: $2,200,000
Questions:
- Calculate the Cost Performance Index (CPI) and Schedule Performance Index (SPI).
- Based on CPI and SPI, evaluate the project’s performance and suggest corrective actions if needed.
- Forecast the total cost at completion using the CPI.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
