Question: A project manager is overseeing a project with a total budget of $6,000,000. The project is halfway through its timeline with the following costs incurred:

A project manager is overseeing a project with a total budget of $6,000,000. The project is halfway through its timeline with the following costs incurred:

  • Actual Costs to Date: $3,000,000
  • Planned Value to Date: $3,200,000
  • Earned Value to Date: $2,800,000

Questions:

  1. Calculate the Cost Performance Index (CPI) and Schedule Performance Index

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!