Question: A project manager is planning a schedule. One task involves installing 1 6 new computers in a building. The project manager is initially unsure of

"A project manager is planning a schedule. One task involves installing 16 new computers in a building. The project manager is initially unsure of how long it takes to install this type computer, so they consult an IT professional who provides an overall estimate of 5 days. What stage of schedule management does this exemplify? "
Estimate activity durations
Sequence activities
Control schedule
Plan schedule management