Question: A project manager is trying to coordinate all the tasks on the project and has determined the following: Task 1 can start immediately and has

A project manager is trying to coordinate all the tasks on the project and has determined the following:

Task 1 can start immediately and has an estimated duration of 2 weeks.

Task 2 can start after task 1 and has an estimated duration of 8 weeks.

Task 3 can start after task 2 is completed and has an estimated duration of 8 weeks.

Task 4 can start after task 1 is completed and must be completed when task 3 is completed. Its estimated duration is 16 weeks.

What is the duration of the critical path for this project? (Hint: Drawing a network diagram will help you arrive at the correct answer!)

A. 8

B. 18

C. 9

D.10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!