Question: A project manager is trying to coordinate all the tasks on the project and has determined the following: Task 1 can start immediately and has
A project manager is trying to coordinate all the tasks on the project and has determined the following:
Task 1 can start immediately and has an estimated duration of 2 weeks.
Task 2 can start after task 1 and has an estimated duration of 8 weeks.
Task 3 can start after task 2 is completed and has an estimated duration of 8 weeks.
Task 4 can start after task 1 is completed and must be completed when task 3 is completed. Its estimated duration is 16 weeks.
What is the duration of the critical path for this project? (Hint: Drawing a network diagram will help you arrive at the correct answer!)
A. 8
B. 18
C. 9
D.10