Question: A project manager is working on a large two - year IT project. Al the end of the first year, the project is two months
A project manager is working on a large twoyear IT project. Al the end of the first year, the project is two months behind schedule because the interface programming is taking longer than planned. The sponsor will not extend the deadline or reduce the scope. However, the sponsor is willing to increase the budget.
Which schedule compression technique can this project manager use?
o Fasttracking o Crashing
Determining the critical path
Resource leveling