Question: A project manager is working with the sponsor to develop a new project charter. To speed up the completion of the project, the sponsor wants

A project manager is working with the sponsor to develop a new project charter. To speed up the completion of the project, the sponsor wants to create 3 teams who will work 24-hours a day in three shifts. The work environment is expected to be hazardous conditions. Where should the project manager document the request in the project charter?