Question: A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Question 22 options:
Revise the project management plan and move the task to a time when the technical resource will be available.
Consult the risk register for an appropriate planned risk response and implement. Most Voted
Review the business requirement with stakeholders and exclude the task assigned to the technical resource.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!