Question: A project manager meets with a team member s functional manager to gather input before the project manager addresses the individual s inadequate performance. What

A project manager meets with a team members functional manager to gather input before the project manager addresses the individuals inadequate performance. What type of structure does this organization use?
Functional
Weak matrix
Strong matrix
Projectized