Question: A project manager notices that $ 1 , 0 0 0 worth of work that was scheduled to be completed at this time has not

A project manager notices that $1,000 worth of work that was scheduled to be completed at this time has not been accomplished. They know this by looking at the Group of answer choices SV. EAC. PCIB. TCPI. EV.