Question: A project manager oversees a project to update a school's art room. Which of the following is NOT a change to the project that needs
A project manager oversees a project to update a school's art room. Which of the following is NOT a change to the project that needs to be managed? A.) The school adds a request for built-in shelving to organize artwork. B.) The art teachers choose new wall decals to match the new paint color. C.) The school decides to add a utility sink in the corner instead of a cabinet. D.) The newly hired school principal wants to pause the project until the next school year. Submit My