Question: A project manager oversees a project to update a school s art room. Which of the following is NOT a change to the project that

A project manager oversees a project to update a schools art room.
Which of the following is NOT a change to the project that needs to be managed?
a.)
The art teachers choose new wall decals to match the new paint color.
b.)
The school decides to add a utility sink in the corner instead of a cabinet.
c.)
The newly hired school principal wants to pause the project until the next school year.
d.)
The school adds a request for built-in shelving to organize artwork.