Question: A project manager performs Earned Value Analysis and finds the following values: EV = 100,000; PV = 125,000; AC = 100,000 a. The project is

 A project manager performs Earned Value Analysis and finds the following

A project manager performs Earned Value Analysis and finds the following values: EV = 100,000; PV = 125,000; AC = 100,000 a. The project is behind schedule and costs exceed budget b. The project is on schedule but costs exceed budget c. The project is behind schedule but on budget d. The project is on schedule and on budget page Next page