Question: A project manager reported the following earned value data: PV. $15,400,000 EV: $14,500,000 AC; $14,500,000 What does this mean ? A project manager reported the

A project manager reported the following earned value data: PV. $15,400,000 EV: $14,500,000 AC; $14,500,000 What does this mean ?
A project manager reported the following earned
A project manager reported the following eamed value data PV $15,400,000 EV. $14,500,000AC$14,500,000 What 6005 ins mean? The project is over budget and on schedule. The project is under budget and on schedule The project is on budget, but behind schedule. The project is on budget and ahead of schedule