Question: A project manager sends out an anonymous team survey for feedback after a customer reports they re not happy with a product feature. Then, the
A project manager sends out an anonymous team survey for feedback after a customer reports theyre not happy with a product feature. Then, the project manager calls a team meeting to discuss the feedback in the survey. During the meeting, the project manager asks the team to use we language instead of you language. At the end of the meeting, the team discusses what lessons the team will carry into future work.
Which three retrospective best practices are the project manager and team following?
Be blameless with teammates
Change perspective
Dont focus only on the negative
Use a timeboxed agenda