Question: A project manager uses Earned Value Management ( EVM ) to assess a projects financial health. What does EVM primarily help them determine?The amount of
A project manager uses Earned Value Management EVM to assess a projects financial health. What does EVM primarily help them determine?The amount of profit generated by the project at any given time.The comparison between actual costs and planned budget, as well as project progress.The future estimated costs after the project is complete.The teams satisfaction with current budget allocations.