Question: A project manager wanted to reduce eight weeks from the projected completion time of the GTR Project in Jakarta, indonesia. 1. Fill in the blanks
A project manager wanted to reduce eight weeks from the projected completion time of the GTR Project in Jakarta, indonesia.
1. Fill in the blanks and based on information provided in the table, answer all questions:
| Activity | Predecessor | Normal Time | Normal Cost ($) | Crash Time | Crash Cost ($) | Time Reduction | Crashing Cost Per Week ($) |
| A | - | 2 | 12,000 | 5 | 13,000 | ||
| B | - | 5 | 50,000 | 7 | 64,000 | ||
| C | - | 1 | 4,000 | 5 | 7,000 | ||
| D | B | 10 | 16,000 | 12 | 20,000 | ||
| E | A,D | 3 | 125,000 | 15 | 200,000 | ||
| F | C | 6 | 10,000 | 9 | 16,000 | ||
| G | E,F | 8 | 500,000 | 9 | 530,000 | ||
| Totals | - | - | |||||
2.Calculate the activity slacks and determine which activities are on the critical path:
| Activity | Earliest Start | Latest Start | Earliest Finish | Latest Finish | Slacks | Critical Path |
3. Why is it important for managers to know where the slack is in their projects?
4. Draw the gantt chart for the new duration.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
