Question: A project manager wants to speed up a project schedule. The project manager is willing to spend more money but is not willing to increase
A project manager wants to speed up a project schedule. The project manager is willing to spend more money but is not willing to increase risks to the project. Given the above, what is the most appropriate method should this project manager should consider to speed up a project schedule?
Group of answer choices
Crashing.
Fast tracking.
None of these options.
The project manager should add additional buffer time to all activities.
Crashing and fast tracking at the same time.