Question: A project manager who is dealing with a project with activities with severe risks that require scarce resources and who is attempting to provide a
A project manager who is dealing with a project with activities with severe risks that require scarce resources and who is attempting to provide a cushion against potential project delays should consider using:
management reserves
budget reserves
time buffers
variable project scope prevention techniques
risk retention strategies