Question: A project manager working on the Project Scope Management processes is operating at the Plan Scope Management process, where he is using all of the

A project manager working on the Project Scope Management processes is operating at the Plan Scope Management process, where he is using all of the following inputs excluding
Select one:
A. EEF
B. Project Charter
C. Requirements Documentation
D. Project Management Plan