Question: A project manager working with her team has developed the following list of tasks and estimates of duration time. Create a AON diagram, identify the
A project manager working with her team has developed the following list of tasks and estimates of duration time.
Create a AON diagram, identify the critical path and calculate the expected project duration
Estimate the additional weeks she requires to be 95% confident of completion date
If the customer requests the project be delivered a week early, what is the chance that it can be done with the same resources?
| Task | Predecessors | T optimistic | T Most Likely | T Pessimistic |
| A | 3 | 4 | 5 | |
| B | A | 4 | 8 | 15 |
| C | A | 2 | 4 | 6 |
| D | A | 4 | 8 | 12 |
| E | B | 7 | 9 | 14 |
| F | C,B | 2 | 5 | 8 |
| G | E,D | 5 | 7 | 12 |
| H | F,G, I | 4 | 7 | 10 |
| I | D | 3 | 6 | 9 |