Question: 3. A project manager working with her team has developed the following list of tasks and estimates of duration time. a. Create a AON diagram,

3. A project manager working with her team has developed the following list of tasks and estimates of duration time.

a. Create a AON diagram, identify the critical path and calculate the expected project duration

b. Estimate the additional weeks she requires to be 95% confident of completion date

c. If the customer requests the project be delivered a week early, what is the chance that it can be done with the same resources?

ANSWER THE QUESTION WITH I AS THE LAST ACTIVITY period.

TIME
Task Predecessors Optimistic Most Likely Pessimistic
A 3 4 5
B A 4 8 15
C A 2 4 6
D A 4 8 12
E B 7 9 14
F C,B 2 5 8
G E,D 5 7 12
H F,G, I 4 7 10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!