Question: A project network with 1 1 activities and 1 5 directed arcs is shown. Activity Start is connected to activity A , to activity B

A project network with 11 activities and 15 directed arcs is shown.
Activity Start is connected to activity A, to activity B, and to activity C.
Activity A is connected to activity D and to activity G.
Activity B is connected to activity D and to activity E.
Activity C is connected to activity E.
Activity D is connected to activity F.
Activity E is connected to activity H.
Activity F is connected to activity G and to activity H.
Activity G is connected to activity I.
Activity H is connected to activity I.
Activity I is connected to activity Finish.
Activity Finish has no arcs directed to other activities.
Activities A-I have numeric values displayed under the Activity label. These values are given below:
A: 6
B: 4
C: 9
D: 4
E: 12
F: 10
G: 3
H: 2
I: 9
Use a forward and a backward pass to determine the critical path, and then fill out the following table. Activity times are in weeks. (For the precedence activities, enter your answers as comma-separated lists. If an activity does not have immediate predecessors, enter NONE.)
Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 29 weeks more or less than 50%?
A project network with 1 1 activities and 1 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!