Question: To help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. In addition,
To help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. In addition, they have estimated the time of each activity in weeks
A project network with activities and directed arcs is shown.
Activity Start is connected to activity A and to activity B
Activity A is connected to activity C and to activity D
Activity B is connected to activity E
Activity C is connected to activity H
Activity D is connected to activity F and to activity G
Activity E is connected to activity F and to activity G
Activity F is connected to activity H
Activity G is connected to activity Finish.
Activity H is connected to activity Finish.
Activity Finish has no arcs directed to other activities.
Activity A B C D E F G H
Time
a
Identify the critical path. Enter your answers as a commaseparated list.
b
How much time in weeks will be needed to complete this project?
weeks
c
Can activity D be delayed without delaying the entire project? If so by how many weeks? If the activity can not be delayed, enter
weeks
d
Can activity C be delayed without delaying the entire project? If so by how many weeks? If the activity can not be delayed, enter
weeks
e
What is the schedule for activity E in weeks
Earliest Start
weeks
Latest Start
weeks
Earliest Finish
weeks
Latest Finish
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock