Question: A project requires the tasks shown in the table below to be completed. The duration column shows the number of weeks estimated for one person

A project requires the tasks shown in the table below to be completed. The duration column
shows the number of weeks estimated for one person to complete the task.
Answer the following questions. Do not use a software project management tool such as
Microsoft Project to assist in either drawing the diagrams or in computing solutions.
(1) Create an activity network diagram for the project tasks, identify the critical path,
and calculate its length.
(2)
Draw a bar chart (also known as a Gantt chart) showing the duration of each task,
assuming that each task starts at the earliest opportunity.
(3)
For each task not on the critical path, by how much could the start be delayed
assuming that each task starts at the earliest opportunity?
(4)
Assuming that each task will be undertaken by a single person, create a staff
allocation chart that allocates the work to John, Kate and Mary in such a way that each task is
undertaken as soon as possible.
 A project requires the tasks shown in the table below to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!