Question: A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the
A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the task.
| Task | Duration | Depend on |
| T1 | 1 | |
| T2 | 3 | |
| T3 | 5 | |
| T4 | 3 | T1 |
| T5 | 2 | T1 |
| T6 | 2 | T1,T3 |
| T7 | 1 | T2,T3 |
| T8 | 3 | T4,T5,T6 |
| T9 | 3 | T5,T7 |
| T10 | 2 | T7 |
| T11 | 2 | T8 |
| T12 | 3 | T8,T9 |
| T13 | 2 | T10 |
Answer the questions below. These activities are intended to develop and assess your understanding of the method, so please do not use a software project management tool such as Microsoft Project to assist in either drawing the diagrams or in computing solutions.
Questions :
Assume 4 engineers, Bob, Sue mary and frank, work on the project and task of length 2 weeks or more can be worked upon by either one or two engineers. if two engineers work in a task their individual efforts must add to the listed total duration , but each must do at least one week of work. Allocate tasks to them to complete the project in the shortest possible time. Show this graphically on a staff allocation chart.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts