Question: A project schedule has the following characteristics: Activity Time ( Weeks ) Activity Time ( Weeks ) 1 - 2 4 5 - 6 4

A project schedule has the following characteristics:
Activity Time (Weeks) Activity Time (Weeks)
1-245-64
1-315-78
2-416-81
3-417-82
3-568-105
4-959-107
1) Compute earliest start time (Es) and latest finish time (Lf) for each event.
2) Compute Total float and critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock