Question: d ) A project schedule has the following characteristics Activity Time ( Weeks ) 1 - 2 1 3 Page 2 of 1 3 3
d A project schedule has the following characteristics Activity Time Weeks
Page of
O S Required: Draw a network to represent the above data Determine the critical path of the project and the expected project length