Question: A project team has a construction plan containing activities with uncertain durations, including precedence constraints. After running a simulation of this plan 50 times, the

A project team has a construction plan containing activities with uncertain durations, including precedence constraints. After running a simulation of this plan 50 times, the mean duration was found to be 200 days, and the standard deviation was found to be 10 days. Can we say, with 95% confidence, that the true mean duration is not 205 days? What about with 99% confidence? Please justify your answers

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!