Question: A project team has identified a defect in a project deliverable. Which quality control tool can be used to identify the cause? Checksheet Control chart
A project team has identified a defect in a project deliverable. Which quality control tool can be used to identify the cause?
Checksheet
Control chart
Ishikawa Diagram
SWOT analysis