Question: A project team has identified a risk with high probability and high impact associated with the complexity of the scope of a project. The project
A project team has identified a risk with high probability and high impact associated with the complexity of the scope of a project. The project manager worked with the project sponsor to alter the scope of the project. The project manager has adopted a risk strategy of
Risk transfer.
Risk reduction.
Risk avoidance.
Risk exploitation.