Question: Answer the question based on the following case study: The Field Service Engineer (FSE) at RedGate Technology had called an escalation Level 4 meeting to

Answer the question based on the following case study:

The Field Service Engineer (FSE) at RedGate Technology had called an escalation Level 4 meeting to resolve a computer failure issue during the project tool upgrade for imaging and wafer transfer improvement. The companys escalation process requires that the FSE escalate the problem, if it has not been resolved after six hours. The escalation is now closed; however, the tool was down for three days, which means daily schedule of the upgrade may need to be revisited. The tool at the RedGate Technology site is the first tool to be upgraded so the team wants to capture as much learning experience as possible to make the next upgrades run more smoothly. This is a case about the unknown project problem that suddenly occurred and how risk planning prepared the team for mitigation of damage, even though a root cause was not known.

THE MEETING

The project update meeting with the core team is underway:

  • Product Engineer: Adam McAllister

  • Technical Engineer: Donna Nolan

  • Systems Engineer: Calvin James

  • Project Manager: Jason Orange

  • Program Manager: Julia Gallagher

Jason: Hi everyone. Thanks for coming. Julia suggested we meet and review our upgrade schedule. We have another tool to be upgraded in two months so we should make quick changes on any design or work instructions that need to be improved. Donna sent out the escalation report describing what happened and the root cause of the issue.

Donna: Yes, I sent it to the team as well as the Field Service Engineers (FSE) at the site. Calvin and Adam are working on retesting the computer and identifying the root cause, and the fix, so that we know what to do if it happens again. I hope it wont happen again, however.

Jason: Good. It sounds like everything is under control now in terms of troubleshooting the tool.

Calvin: Well, actually, I havent had any luck on reproducing the error that they saw at the site. I talked to Nick Filan, the lead FSE, about what happened. He told me that it was the blue screen phenomena the computer worked fine and then the screen was blue all of the sudden. They were not able to recover the error at all.

Jason: Have you seen this happening before?

Calvin: I dont have much experience on this tool so I dont have any historical issues that Ive seen with my own eyes. I couldnt reproduce what they said was happening prior to the blue screen phenomena, but I couldnt get the blue screen on my simulator.

Jason: Yes, I realized Steve Huggins did not give you any briefing before he left the company. It would be nice if he had documented everything that hed seen when designing this system.

Adam: I havent heard of it happening before. Calvin and I can ask other engineers to get their input on this issue. The bad thing is that this computer is a new design so it has not been implemented on other product lines. I dont know what kind of information I can get from asking around other engineers.

Jason: Well, it never hurts to try. Let me know if youre running into more issues. Now we can update the schedule to accommodate the time lost during troubleshooting.

BACKGROUND

The IEM Company is a high - tech company producing customized Ion and Electron Microscopes. The applications of their products can be used in a variety of fields, from academia to high tech industries. Their customers are given the options of customizing the product to meet specific process needs. The companys financial profile shows that their sales revenue for last year exceeds $ 400 million. The company is currently upgrading tools in the field for improvement in the imaging and wafer transfer system. This is required to grow the market size and to meet customers satisfaction.

RISK PLAN

Julia: Jason, can you give a brief update on how we are on the schedule?

Jason: Sure. From the Gantt chart that I sent you yesterday, we are currently three days behind schedule. Rob Carter, the process engineer at RedGate, told me that the tool handover to production cannot be delayed due to production backlog. We may need to add a second shift for the upgrade to mitigate the scheduling issue.

Julia: What is the original upgrade timeline, Jason?

Jason: The tool is promised to be ready for production within two weeks.

Julia: Before we move forward on deciding what to do next, can we review your project scope and risk planning matrix? Ive only seen your scheduling chart but did not have a chance to review the whole package when I approved this project.

Jason: Yes, I was aware that Marketing and Sales already promised the date to the customer before I finished creating this Gantt chart. I did not know the change on the timeline and date until I asked Markus if there were any changes on the project. If only our communication could be improved . . .

Julia: Well, that was in the past, now we have to create a mitigation plan for it. Have we figured out what the root cause of the problem is?

Jason: No, our original Systems Engineer for this project, Steve Huggins, left the company two weeks ago. He only gave a two - week notice and then was out of the office the last week before he left to use up his vacation days. Calvin James replaced him for this project; however, he is quite new to this product line so he is still learning on the go. He has not figured out the root cause of the problem yet.

Julia: Interesting. Can you describe what you included in the risk plan?

Jason: Yes, the core team brainstormed what should be considered risks for this project. We were focusing more on the design and supply chain, however. The implementation plan was assumed to be handled by the Technical Group (TSG). We grouped the risk plan per main category, for example, in Design, we split up the risk plans to Hardware and Software groups. We did it this way so that we can manage it much easier since the activity list from the WBS is quite big. We used discrete estimation for probability and risk impact. The qualitative data was per our best estimate learning from past projects. Steve Huggins had been involved in two major tool improvement projects in the past so he was very knowledgeable in this area. Heres the risk plan for the Software activity list (see Table below).

Julia: So you excluded most activities in the WBS from the risk plan?

Jason: Thats right. We thought we should only list activities with medium and high risk. Whats the point of recording low - risk activities if theyre not going to affect the project by much? Anyway, you can see that we did include computer testing as part of our WBS.

Julia: Yes, however, did you guys test for long - term reliability? I know we dont know why we had blue screen problem in the field but you might have caught it, if you tested the part for a long period of time.

Jason: No, we didnt do that. We only tested the first article for making sure most features worked because we didnt have time for a long - term reliability test.

Julia: Hmm . . . thats a little odd. Did you find out the plan developed by TSG?

Jason: No. When I submitted the project charter, our scope was only on the design, development, and testing.

Donna: The TSG are responsible for performing the task of upgrading the tool, however, since you are the project manager, you are the one responsible for connecting the whole areas, including field implementation. I was not aware that you assumed we were going to do the whole field implementation plan, while you were working on the upgrade schedule.

Julia: I can see theres a disconnect among core team members . . .

Table Software risk plan

Task

Risk description

Probability *

Impact **

Risk score

(P+2xI)

Preventive action

Trigger points

Contingent

Owner

Review marketing

requirement

document

Marketing requirement

does not include all

customers requests

2

4

10

Review marketing

Requirement document with the customers

Process engineer before design phase kicks off

No customers process engineer available for review meeting by June 30th

Escalate

to the

manager

for their POC availability

Project manager

Identify required changes on computer configuration

Not enough knowledge on new process to be implemented

3

4

11

Review other tools application to see if we can use their

concept

Not enough

data to determine what application can be used as an example by June 30th

Contact

customers expert to see if theres any

current applications similar to the new process

Software engineer

Determine time

and cost budget

for new computer

Supplier cant meet

our short timeline

request to implement changes

4

5

14

Send specifications prior to design

reviews

Suppliers timeline is 2 weeks longer

Than expected

Send specifications to a few suppliers and go with the fastest delivery timeline.

Sourcing rep

Create success measures for

computer

tests

Success measures do not reflect all actual use cases

Review success measures with other software

Engineers for fresh - eye review

No feedback

from other software engineers by July 10th

Escalate to project manager for help in gathering resources

Software engineer

*Probability (Discrete Estimation): 1 = Very Unlikely, 2 = Low Likelihood, 3 = Likely, 4 = Highly Likely, 5 = Near Certain

**Risk Impact (Discrete Estimation): 1 = Very Low Impact, 2 = Low Impact, 3 = Medium Impact, 4 = High Impact, 5 = Very High Impact

Ques:

What was wrong in the companys risk identification process? Identify and discuss the issues 300 words.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!