Question: A project team has started gathering information necessary to develop a project networkpredecessor activities and activity time in days. The results of their meeting are

A project team has started gathering information necessary to develop a project networkpredecessor activities and activity time in days. The results of their meeting are found in the following table:
\table[[Activity,Description,Duration,Predecessor],[1,A,10,],[2,B,10,1],[3,C,8,1],[4,D,4,2,3],[5,E,7,4],[6,F,10,5],[7,G,6,6],[8,H,10,7],[9,I,15,7],[10,J,10,8,9],[11,K,5,10],[12,L,3,11]]
Part A. Create a network based on the above information. How long will the project take? What is the critical path?
Part B. Upon further review the team recognizes that they missed three finish-to-start lags. Activity B will only involve 2 days of work but it will take 8 days for the parts to be delivered. Likewise, Activity H will take 2 days of work and 8 days for delivery and Activity I needs 2 days of work and 13 days for delivery. Reconfigure the schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule? On the amount of work required to complete the project?
 A project team has started gathering information necessary to develop a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!