Question: The CyClon project team has started gathering information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting

The CyClon project team has started gathering information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in Table 1.

(a) Complete the Microsoft Project Entry Table below based on the information given in Table 1.

(b) How long will the project take?

(c) What is the critical path for the project?

(d) Upon further review the team recognizes that they missed three finish-to-start lags.Procure prototype parts will involve only 2 days of work but it will take 8 days for the parts to be delivered. Likewise, Order stock components will take 2 days of work and 8 days for delivery and Order custom components 2 days of work and 13 days for delivery.

Reconfigure the Cyclon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule, and on the amount of work required to complete the project?

 The CyClon project team has started gathering information necessary to develop
a project network-predecessor activities and activity time in days. The results of
their meeting are found in Table 1. (a) Complete the Microsoft Project
Entry Table below based on the information given in Table 1. (b)

Pasukan projek CyClon telah mula mengumpul maklumat yang diperlukan untuk membangunkan aktiviti pendahulu-rangkaian projek dan masa aktiviti dalam hari. Keputusan mesyuarat mereka terdapat dalam Jadual 1: The CyClon project team has started gathering information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in Table 1 : (a) Lengkapkan Microsoft Project Entry Table di bawah berdasarkan maklumat yang diberikan dalam Jadual 1. Complete the Microsoft Project Entry Table below based on the information given in Table (b) Berapa lama projek itu akan mengambil masa? How long wil the project take? (c) Apakah laluan kritikal projek tersebut? (2 markah/marks) What is the critical path for the project? (2 markah/marks) (d) Selepas semakan lanjut, pasukan menyedari bahawa mereka terlepas tiga ketinggalan dari penamat ke permulaan. Perolehan bahagian prototaip akan melibatkan hanya 2 hari kerja tetapi ia akan mengambil masa 8 hari untuk bahagian tersebut dihantar. Begitu juga, Pesanan komponen stok akan mengambil masa 2 hari bekerja dan 8 hari untuk penghantaran dan Pesanan komponen tersuai 2 hari kerja dan 13 hari untuk penghantaran. Konfigurasikan semula jadual Siklon dengan memasukkan tiga ketinggalan penamat-untuk-mula. Apakah kesan kelewatan ini pada jadual asal, dan pada jumlah kerja yang diperlukan untuk menyiapkan projek? Upon further review the team recognizes that they missed three finish-to-start lags. Procure prototype parts will involve only 2 days of work but it will take 8 days for the parts to be delivered. Likewise, Order stock components will take 2 days of work and 8 days for delivery and Order custom components 2 days of work and 13 days for delivery. Reconfigure the Cyclon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule, and on the amount of work required to complete the project? (3 markah/marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!