Question: A project team is performing extremely well when it comes to delivering the value added features to the customer in each sprint. However, they are

A project team is performing extremely well when it comes to delivering the value added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current. Which action should the project manager take? Focus on the documentation after the features are delivered. Assign a dedicated resource to work on the documentation during the project. Create a specific sprint to deliver the project documentation. Make documentation a standard part of the definition of done (DoD)