Question: A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing
A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current. Which action should the project manager take? Focus on the documentation after the features are delivered. Create a specific sprint to deliver the project documentation. Make documentation a standard part of the definition of done (DoD). Assign a dedicated resource to work on the documentation during the project