Question: A project team is using forecasting to determine the estimate at completion for their project. The spending has been very consistent and is expect to
A project team is using forecasting to determine the estimate at completion for their project. The spending has been very consistent and is expect to remain so. The CPI is 1.10. The original budget at completion was $1 Million. What is the new Estimate at Completion (EAC)?
Group of answer choices
(A) $1,111,111
(B) $909,091
(C) It remains unchanged
(D) $1,100,000