Question: A project that has an expected completion time of 40 weeks and a standard deviation of 3.3 weeks. What is the probability that the project
A project that has an expected completion time of 40 weeks and a standard deviation of 3.3 weeks. What is the probability that the project is finished in 44 weeks or more? P(t) = P(t>=44)
(Round your response to three decimal places)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock