Question: Limbo Technologies has embarked on another project that has an estimated completion time of 40 weeks and a standard deviation of 5 weeks. It is
Limbo Technologies has embarked on another project that has an estimated completion time of 40 weeks and a standard deviation of 5 weeks. It is estimated that the project completion time is normally distributed.
(a) What is the probability of finishing the project in 38 weeks or less?
(b) The due date for the project is set that there is a 90% chance that it will finish by this date. What is the due duration?