Question: A project that should have been 9 0 percent complete by now is only 8 4 percent complete. The total project budget is US$ 1

A project that should have been 90 percent complete by now is only 84 percent complete. The total project budget is US$110,000, and the actual cost of work performed (ACWP) is US$82,000.
What is the schedule performance index (SPI) and cost performance index (CPI) for this project? Select one.
Question 9 options:
The SPI is 0.93, and the CPI is 1.13.
The SPI is 0.96, and the CPI is 1.18.
The SPI is 1.15, and the CPI of .93.
The SPI is 1.07, and the CPI is 0.99.