Question: A project that should have been 9 0 percent complete by now is only 8 4 percent complete. The total project budget is US$ 1
A project that should have been percent complete by now is only percent complete. The total project budget is US$ and the actual cost of work performed ACWP is US$
What is the schedule performance index SPI and cost performance index CPI for this project? Select one.
Question options:
The SPI is and the CPI is
The SPI is and the CPI is
The SPI is and the CPI of
The SPI is and the CPI is