Question: A project was budgeted at $ 1 , 0 0 0 , 0 0 0 . Meanwhile, the project is executed, and the following current
A project was budgeted at $ Meanwhile, the project is executed, and the following current figures have been assessed: PV: $ EV: $ AC: $ Assuming that the cost variance was caused by onetime cost drivers, which are no longer effective in estimations, what estimate at completion EAC can you derive from these figures?