Question: A project was budgeted at $ 1 , 0 0 0 , 0 0 0 . Meanwhile, the project is executed, and the following current

A project was budgeted at $1,000,000. Meanwhile, the project is executed, and the following current figures have been assessed: PV: $500,000 EV: $450,000 AC: $550,000. Assuming that the cost variance was caused by one-time cost drivers, which are no longer effective in estimations, what estimate at completion (EAC) can you derive from these figures?
Question 1Answer
a.
$1,222,222
b.
$1,000,000
c.
None of the provided figures
d.
$900,000
e.
$1,100,000