Question: A project was estimated to cost $ 200,000 with a timeline of 10 months. Due to a shipment delay, the schedule was slightly,r delayed. This
A project was estimated to cost $ 200,000 with a timeline of 10 months. Due to a shipment delay, the schedule was slightly,r delayed. This was however made up by receiving the first batch of materials for the project by air. The net result was that there was some additional cost in the project. At the end of the second month, the Project Manager reviews the project and finds that the project is 20% complete and Actual Costs are $ 50,000. The Estimate to complete (ETC) for the project would now be?
Step by Step Solution
3.54 Rating (144 Votes )
There are 3 Steps involved in it
The budget at completion BAC 200000 The actual costAC 50000 The earned valueEV ... View full answer
Get step-by-step solutions from verified subject matter experts
