Question: A project with 7 activities is shown below. STA F FIN The duration of activities A, B, C, and D are 21, 10, 12, and

A project with 7 activities is shown below. STA F
A project with 7 activities is shown below. STA F FIN The duration of activities A, B, C, and D are 21, 10, 12, and 19 days, respectively. On the other hand, the duration of activities E, F, and G are 14, 32, and 21 days. Assuming the project starts at the end of day 0, the latest finish time of activity B will be at the end of day