Question: A project with 7 activities is shown below. STA D V2 F FIN The duration of activities A, B, C, and D are 23, 22,

A project with 7 activities is shown below. STA D
A project with 7 activities is shown below. STA D V2 F FIN The duration of activities A, B, C, and D are 23, 22, 10, and 27 days, respectively, On the other hand, the duration of activities E, F, and G are 22, 30, and 29 days. Assuming the project starts at the end of day 0, the earliest finish time of activity G will be at the end of day