A project with a total budget of $100,000 is underway, but not finished. The project manager calculates
Fantastic news! We've Found the answer you've been seeking!
Question:
A project with a total budget of $100,000 is underway, but not finished. The project manager calculates that sixteen work packages that were budgeted at $40,000 in total have been completed, and that no others have begun. Accounting advises the manager that $50,000 has been spent in completing those 16 work packages. According to the project plan $45,000 should have been spent to date in order to finish 18 work packages.
a) what is EV in dollars
b) what is Cv in dollars
c) what is sv in dollars
d) what is CPI
e) what is EAC