Question: A project with six activities is in its performing phase. At the end of week 10, you have the following information: Activity A, TBC =
A project with six activities is in its performing phase. At the end of week 10, you have the following information: Activity A, TBC = 45841 dollars, 80 percent completed Activity B, TBC = 36745 dollars, 74 percent completed Activity C, TBC = 24980 dollars, 83 percent completed Activity D, TBC = 27000 dollars, 48 percent completed Activity E, TBC = 60571 dollars, 0 percent completed Activity F, TBC = 54852 dollars, 0 percent completed You also know that a total of 99660 dollars has been spent on the project. At the end of week 10, the cumulative budgeted cost should be 113318 dollars. NOTE: Do not use any comma in your answer. Use at least 4 decimals. At the end of week 10, the project cost performance index is A project has 79 activities but only 11 activities are discussed here. Activity E, duration = 26 days, IP = unknown Activity F, duration = 17 days, IP = unknown Activity G, duration = 31 days, IP = unknown Activity K, duration = 15 days, IP = E, F Activity M, duration = 27 days, IP = E, F Activity N, duration = 16 days, IP = G If you know that LF of T = 75, LF of U = 87, and, LF of X = 83, then: LS of K = LS of M= LS of N = LS of P = LS of E = LS of F = LS of G = LS of H = A project with six activities is in its performing phase. At the end of week 10, you have the following information: Activity A, TBC = 45841 dollars, 80 percent completed Activity B, TBC = 36745 dollars, 74 percent completed Activity C, TBC = 24980 dollars, 83 percent completed Activity D, TBC = 27000 dollars, 48 percent completed Activity E, TBC = 60571 dollars, 0 percent completed Activity F, TBC = 54852 dollars, 0 percent completed You also know that a total of 99660 dollars has been spent on the project. At the end of week 10, the cumulative budgeted cost should be 113318 dollars. NOTE: Do not use any comma in your answer. Use at least 4 decimals. At the end of week 10, the project cost performance index is A project has 79 activities but only 11 activities are discussed here. Activity E, duration = 26 days, IP = unknown Activity F, duration = 17 days, IP = unknown Activity G, duration = 31 days, IP = unknown Activity K, duration = 15 days, IP = E, F Activity M, duration = 27 days, IP = E, F Activity N, duration = 16 days, IP = G If you know that LF of T = 75, LF of U = 87, and, LF of X = 83, then: LS of K = LS of M= LS of N = LS of P = LS of E = LS of F = LS of G = LS of H =