Question: A project with time uncertainty has work breakdown structure, precedence relationships, and activity times as follows. Assume that activities are started as early as possible,
A project with time uncertainty has work breakdown structure, precedence relationships, and activity times as follows. Assume that activities are started as early as possible, i.e. no delays.
| ID | IP | Activity Time (months)
|
| A | - | 4 |
| B | A | 8 |
| C | A | 3 months with probability of 0.4 6 months with probability of 0.4 9 months with probability of 0.2 |
You need to show project networks, steps, and results in answering the following questions.
(a)[2] What is the shortest project completion time among the three possible scenarios?
(b)[2] What is the longest project completion time among the three possible scenarios?
(c)[1] What is the expected project completion time? (A weighted average among the three scenarios with probabilities specified in the table)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts