Question: Question 12 (15 points) Scroll further down to submit your answers A project with time uncertainty has work breakdown structure, precedence relationships, and activity times
Question 12 (15 points) Scroll further down to submit your answers
A project with time uncertainty has work breakdown structure, precedence relationships, and activity times as follows. Assume that activities are started as early as possible, i.e. no delays.
| ID | IP | Activity Time (months) |
| A | - | 8 |
| B | A | 5 |
| C
| A
| 4 months with probability of 0.4 7 months with probability of 0.1 9 months with probability of 0.5 |
(a)[5] What is the shortest project completion time among the three possible scenarios? (For example: enter 15 for 15 months)
(b)[5] What is the longest project completion time among the three possible scenarios? (For example: enter 15 for 15 months)
(c)[5] What is the expected project completion time? (A weighted average among the three scenarios with probabilities specified in the table) (For example: enter 13.64 for 13.64 months)