Question: A project with uncertainty has a mean completion time of 48.17 weeks, with a variance of 11.0889 weeks. What is the probability that the project
A project with uncertainty has a mean completion time of 48.17 weeks, with a variance of 11.0889 weeks. What is the probability that the project will finish within 50 weeks? Please put the result in terms of a probability (i.e. a number between 0 and 1), and not a percentage.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts