Question: Estimating probability of project completion using normal distribution 1PERT analysis indicates that a project has a mean completion time of 40 weeks , with a

Estimating probability of project completion using normal distribution

1PERT analysis indicates that a project has a mean completion time of 40 weeks, with a standard deviation of 2.8 weeks. Probability that the project can be finished in 35 weeks: P(X<35)

2Probability that the project will take longer than 42 weeks: P(X>42)

3Probability that the project will take between 39 to 45 weeks to be completed: P(39

4Probability that the project will be finished after 38 weeks: P(X>38)

5You must quote a delivery date to your client. If you wish to have a 97% service level (i.e., 97% chance that you will finish the project by that date), how many weeks from the start of the project should you set as that completion date?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!